Reservoir 17/20 Exterior Coating Replacement

Project Overview


Reservoir 17 & 20 are each 1-million gallon welded-steel water reservoirs located, side by side, in East Bremerton. An exterior coating assessment report was prepared by Northwest Corrosion Engineering in January 2014 which recommends recoating of the exterior of this reservoir.  This project includes removing the existing exterior coating and installing a new exterior coating.  

Reservoir 17 was constructed in 1977; it is 95-feet in diameter and approximately 20 feet in height. Reservoir 20 was constructed in 1981; it is also 95-feet in diameter and approximately 16 feet in height.   

The City anticipates advertising for bids before the end of February. 

Budget


The overall budget for this project is $600,000, including design, construction, etc.

Schedule

Design (in-house) - To be completed by end of January 2018
Bid/Award - February and March 2018
Construction - Mid-May through August 2018