Highway Safety Phase II, PSNS and 2nd St ADA Retrofit Projects

Project Status (Updated August 9, 2017) 


Massana Construction, the City’s contractor, will begin work on this project on Monday, August 14th 2017. The project will be phased, with the new curb ramps installed during the first phase and the above ground electrical components installed at a later date. The typical progress of work for each site during phase 1 will be: demo and prepare the subgrade for the new curb ramps, complete underground electrical work, pour curb and gutter, and then pour the new curb ramps. The schedule for the first intersection is as follows:      

6th Street & Callow Avenue 
  • South side ramps – 8/14/17 to 8/24/17
  • North side ramps – 8/25/17 to 9/6/17
Each intersection will take about 18 days to complete, once Massana finishes an intersection they will move to the next.  The planned order for the remaining intersections is as follows:

  • Burwell Street & Callow Avenue
  • Burwell Street & N. Montgomery Avenue
  • Burwell Street & High Avenue
  • 11th Street & N. Montgomery Avenue
The pedestrian improvements to Burwell Street and Chester Avenue, along with the sidewalk improvements on State Street will run concurrently with the intersections above, however the start date for that work has not been established. Updates for exact start dates will be posted here as soon as they become available.

Traffic will be impacted by lane closures to accommodate the work at each intersection. The lane closures will be localized to the intersection under construction, however they will be in place 24 hours a day. Pedestrian traffic will be routed around the sidewalk closures or detoured to other crossing points. Pedestrians should use extra care when navigating these intersections and be sure to follow the detour signage. Occasionally, flaggers may be utilized to direct traffic on side streets, such as Montgomery Avenue.  
  
The second phase of the project will begin as soon as the above ground electrical components, such as signal poles and push buttons are received. These items are in high demand and lead times for their manufacture are significant, however we are confident that the project can be completed by the end of 2017. More details on the scope and schedule of the second phase work will be posted as the work becomes imminent. 
 

Project Overview 


In December 2014 the City was awarded a Highway Safety Improvement Grant to construct safety improvements at 6 intersections throughout the city. Subsequent to receipt of the grant award, the project scope was revised due to redundant scope with the WSDOT ADA ramp construction on Wheaton Way. The project will construct improvements which include new ADA ramps and pedestrian signals, pavement markings and lighting at the following intersections:  

11th & Montgomery
6th & Kitsap Way
Burwell & Callow
Burwell & Montgomery
Chester & Burwell 
High & Burwell

In addition, the City will complete pedestrian improvements in the vicinity of the State Street Shipyard Pedestrian gate using funds remaining from the Burwell Tunnel Construction project.

Supporting Documentation and Photographs

Schedule

 
Construction will commence when long lead time materials have been procured, late summer to early fall.